The National Grid has been fined £3.2 million after a catastrophic failure in safety procedures left Justin Hollins, a father-of-two, with severe, life-altering injuries. The accident occurred at the Treforest Industrial Estate in Pontypridd, South Wales, where Mr. Hollins, 50, was working on a pylon. A shock of 33,000 volts surged through his body, causing burns to 40% of his skin and leading to nerve damage that affects his mobility. The incident also cost him part of his right buttock.

The accident took place on 3 December 2020, but the fallout continues. Mr. Hollins, a once active man in peak physical condition, endured six operations within ten days of his admission to the hospital. “Every day was a huge battle,” he recalled. The immediate aftermath required round-the-clock care. Though he no longer needs frequent hospital visits, he will remain a burns patient for life. His injuries are not just physical but emotional and psychological, as he faces the uncertainty of the long-term damage inflicted on his internal organs by the high-voltage shock.

A Failing of Duty

National Grid Electricity Distribution (South Wales) Plc and 4 Power Ltd were both held accountable for the incident. Their negligence was cited as the direct cause of the accident. The Health and Safety Executive (HSE) conducted a thorough investigation and uncovered several failures in safety planning and execution.

4 Power Ltd, based in Cheshire, failed in its obligation to properly assess the risks associated with the work on the pylon. Specifically, the investigation found that the arms of the pylon were too short for the job to be performed safely, preventing adherence to industry-standard safety distances. Had these risks been properly identified and addressed, Mr. Hollins’ injuries could have been avoided.

National Grid Electricity Distribution (South Wales) Plc, headquartered in Bristol, was also found culpable for failing to ensure the electricity supply was switched off before work commenced. This oversight was a critical factor leading to the accident.

Legal Ramifications

Both companies admitted to their failings in court. 4 Power Ltd pleaded guilty to breaching Section 2(1) of the Health and Safety at Work Act 1974. The court imposed a fine of £80,000 and ordered them to pay additional costs of £14,123.

National Grid Electricity Distribution (South Wales) Plc pleaded guilty to breaching Regulation 14 of the Electricity at Work Regulations 1989. Their negligence resulted in a much heftier penalty, with a £3.2 million fine and an additional £20,460 in costs.

Impact on the Worker

For Justin Hollins, the consequences of this corporate negligence have been profound. His ability to work and provide for his family has been stripped away. Once an active and healthy man, he now lives with the scars of the accident, both visible and unseen. “I have to live with the physical and mental effects of the accident for life,” Hollins shared. His statement paints a harrowing picture of a man who has lost not just his livelihood but a significant portion of his identity.

Hollins will never forget the day he hung helplessly from the pylon, waiting for his colleagues to rescue him. His body was shattered, and his future irreparably altered. Though he feels fortunate to have survived, the daily battle continues. He endures ongoing physical pain, emotional strain, and the haunting uncertainty of his long-term health prospects.

A Preventable Tragedy

Speaking after the trial, HSE Inspector Rhys Hughes voiced his frustration with the incident. “The injuries sustained by Mr. Hollins have been truly life-changing. He is lucky to be alive. What is so frustrating in incidents like these is if a safe system of work had been in place before the incident, his injuries would have been prevented.” Hughes stressed that those responsible for work environments must ensure the safety of their employees by implementing safe working systems, providing necessary information, and ensuring strict adherence to safety regulations.

This accident, like so many others, could have been avoided with proper foresight and planning. Hughes highlighted the resources available to employers and workers to prevent such tragedies, including free advice and guidance from the HSE’s website.

Industry-Wide Lessons

The case serves as a grim reminder for industries that deal with high-risk environments. The fines imposed on National Grid and 4 Power Ltd are not merely punitive but are meant to send a clear message to other companies: safety cannot be compromised. The costs of failing to follow regulations extend far beyond financial penalties—they result in human suffering that no amount of money can rectify.

As businesses across the UK review their health and safety protocols, it’s crucial they remember the price of neglect. Every accident is preventable if the correct steps are taken. Ensuring that workers are adequately protected isn’t just a legal requirement; it’s a moral one.

The tragedy faced by Justin Hollins underscores the importance of diligence, planning, and adherence to safety standards. His story should serve as a stark warning and a catalyst for change within the industry. The price of negligence is too high, and the consequences are irreversible.

FAQs

What were the immediate causes of the accident that led to Justin Hollins’ injuries?

The immediate causes were the failure to switch off the electricity supply before work commenced and the inadequate assessment of risks associated with the work on the pylon.

How could the accident have been prevented? 

The accident could have been prevented by adhering to safety regulations, including switching off the electricity supply and properly assessing the risks before starting the work.

Why did these safety measures fail?

The safety measures failed due to negligence from both National Grid Electricity Distribution (South Wales) Plc and 4 Power Ltd, leading to a lack of proper risk assessment and failure to switch off the electricity supply.

What role did the National Grid play in this incident? 

National Grid was responsible for ensuring the electricity supply was switched off before work commenced, which they failed to do, leading to the accident.

What were the consequences for the companies involved?

 Both companies were fined for their negligence. 4 Power Ltd was fined £80,000 and National Grid was fined £3.2 million.